Completed in December 2024, the $130 million development by Mayrin Group comprises 42 townhouses over a 5,000 m2 gross floor area.
Designed by DKO and constructed by Growthbuilt, The Archwood Residences offer 4-bedroom townhouses in Roseville, approximately 11 km from Sydney CBD. The development is conveniently located a short distance from Roseville train station, providing good connectivity with the public transport system.
ptc. was engaged by Growthbuilt to assist with traffic engineering services during the construction stage. The collaboration between ptc., Transport for NSW and Growthbuilt was a key aspect of the project.
A gas valve and water services were located beneath an active arterial road and needed to be relocated to facilitate new connections. Our team conducted on-site workshops with TfNSW and Growthbuilt to establish a traffic management solution for the relocation works, including partial road closures and traffic diversions.
The outcome was a Construction Traffic Management Plan and a Traffic Signal Design allowing for the works, which maintained safety and limited the impacts to traffic in the area.
Client: Growthbuilt
Location: Roseville, NSW
Services provided:
- Construction Traffic Management Plan (CTMP) associated with main works and public domain works
- Traffic Signal Design
- Construction and Occupation Certificates (CC and OC)
- Liaise with Transport for NSW
- Road Safety Audit
Image credit: Mayrin Group